The pre-assembly and integral lifting method shortened the assembly time of each single-span bailey beam to 4 hours, boosting construction efficiency by 50%. An IoT monitoring system was deployed to track the settlement, displacement and stress of the trestle in real time, so as to adjust construction parameters dynamically and ensure structural safety.
As a benchmark project for Jiangsu Sujian Road & Bridge in the field of steel temporary bridges for complex deep-water terrain, this project overcame multiple challenges including deep water, exposed rock, strict environmental requirements and tight construction schedule. With optimized technical solutions, efficient construction organization and rigorous management & control, the project was completed successfully. It guaranteed the progress of this key transportation project, and achieved outstanding results in technological innovation, workplace safety and environmental protection.